EMBOSS: Project Meeting (Fri 25th June 2004)
|
Attendees
RFCGR/HGMP:
Alan Bleasby,
Jon Ison,
Gary Williams,
Lion:
Sanger:
EBI:
Peter Rice,
Visitors:
Apologies:
1. Minutes of the last meeting
Minutes of the meeting of 11th Jnue 2004 are
here
2. Software Development
2.1 Compilation failures in committed code
Following 3 recent problems, Alan proposed fines of £5 for code
commits which cause compilation or build failures. This was accepted
by everyone.
As with the original fines for bugs, the money will be used to fund a
future party.
2.2 Release 2.9.0
Alan is testing installation of EMBASSY packages with a
previously installed EMBOSS, as an alternative to installing
in an embassy directory immediately under a source distribution.
Peter committed to updating the feature table for Sanger use before the
release.
2.3 Code cleanup
Peter will give a talk on ACD and code changes next week, to
update everyone on the recent code documentation and ACD standards in
the code cleanup.
3. Documentation & Training
3.1 CCP11 SIG
The CCP11 SIG (special interest group) meeting at ISMB has very few
registrations. It will clash with BOSC and the other SIGs before
ISMB.
3.2 Sourceforge website
The Sourceforge website has been updated. Please check and comment.
The new project address will be publicised as http://emboss.sourceforge.net/
because http://www.emboss.org/ remains owned by Eric Bongcam-Rudloff and is
not under control of the EMBOSS team We hope it will continue to
redirect to the real EMBOSS pages.
4. Administration
No items.
5. User queries and answers
Gary's current list reviewed. Most new issues were already answered.
6. AOB
No items
7. Date Of Next Meeting
Next meeting at 9.30 on July 9th, 2004,